OUR PROJECTS - INDUSTRIAL

In line with the Government’s promotion of life science industries, last decade saw influx of multinational food and drug companies investing in new research and production facilities in Tuas area. SOE had the opportunity to participate in some of these new investments including Wyeth Pharmaceutical Pharma Plant, Schering-Plough Biotech and Tablet facilities, Pfizer Pharmaceutical Infrastructure, Abbott Nutritional Milk Powder Plant, etc.

Construction of these facilities complied with GMP procedures, FDA guidelines, FM requirements and international clean room installation methods for production areas.

Our scope of work in these facilities include HT and LT distribution, transformers, generators, LT MSB, MCC, BMS cabling, Fire Alarm, CCTV, Security system, IT, telephone system, UPS, VFD, etc. We were also involved in production machine hook up, automation implementation, wireless Human-Machine interfacing, etc.

We were also involved in construction of industrial estates such as Paya Ubi Industrial Park, Kaki Bukit Industrial Park, Gemplus Semiconductor plant, to name a few.


 
 PROJECT REFERENCE – INDUSTRIAL
   
Pepperl + Fuchs at Pioneer Turn

P+F @ Pioneer Turn

Owner Pepperl + Fuchs (Mfg) Pte Ltd
M&E Consultant Aecom Singapore Pte Ltd
Main Contractor Soil-Build (Pte) Ltd
Contract Sin $4.85Mil
Jul 2014 – Apr 2016

Novartis Biopharmops at Tuas

Novartis Biopharmops

Owner Novartis Singapore
Pharmaceutical Manufacturing
M&E Consultant Jacobs Engineering
Main Contractor Bovis Lend Lease
Contract Sin $4.208Mil
Dec 2013 – Mar 2015

Alcon Singapore

Owner -
Alcon Singapore Manufacturing
M&E Consultant - Jacobs Engineering
Main Contractor - Bovis Lend Lease
Contract - Sin $10.9Mil (Sep 2009 – Aug 2010)
Manpower Peak - 160 men
Total - 350,000 man-hrs

REC Building & Infrastructure

Owner -
REC Site Services Pte Ltd
M&E Consultant - Flour Corporation
Main Contractor - Bovis Lend Lease
Contract - Sin $34.5Mil (Nov 2008 – Mar 2010)
Manpower Peak - 300 men
Total - 780,000 man-hrs

Abbott Nutrition International

Owner - Abbott Nutrition International
M&E Consultant - Jacobs Engineering
Main Contractor - Bovis Lend Lease
Contract - Sin $15.4Mil (Nov 2006 - Apr 2008)
Manpower Peak - 210 men
Total - 450,000 man-hrs


Schering-Plough Biotech & Tablet Facilities

Owner -
Schering-Plough Ltd
M&E Consultant - Jacobs Lend Lease
Main Contractor - Jacobs Lend Lease
Contract - Sin $11.2 Mil (May 2000 - Dec 2002)
Manpower Peak - 180 men
Total - 230,000 man-hrs